Erskine Park logistics facility required an end of lease make good to be complete within two weeks, ahead of the incoming tenant’s occupation. Engine Room were tasked to tender, programme and manage the fast-tracked delivery programme. With significant damages incurred from a delayed handover Engine Room worked with a highly skilled contractor to develop a programme to ensure all time efficiencies emerged throughout the works.

The works involved, but were not limited to, the demolition of a 500m2 internal cool and freezer rooms, requiring significant slab repairs and alteration to the fire suppressions system.

Two-week onsite delivery programme

Office, Warehouse and Exterior makegood

Demolition of existing cool room and slab repairs

Works completed under CDC

COVID-19 Update

The Engine Room VM team are currently working remotely in an effort to support the safety and wellbeing of our staff and associated communities. Whilst our physical office is closed, we remain connected to our clients and project teams via virtual conferencing and are operating “business as usual”. We’re here to provide support during these uncertain times; please get in contact with our experienced team should you be seeking clarity on the implications of COVID-19 on your project.